Ras El-Bar Shore Protection

• Project description :

• Constructing sea wall 90 m length from stone and sea wall 450 m length from Dolomite , the main layer protection from Dolos weight 6 ton and fill behind breakwater with sand to create area with 24000 m2 ,Constructing submerged breakwater 250 m length and main layer protection from Dolos weight 4 ton ,Supporting 8 break waters with Dolos weight 6 ton using marine equipment (Benton and tug boat).

• The project owner: The Egyptian authority for shore protection
• Supervision : The Egyptian authority for shore protection
• Project Duration : 2 Years
• Contract Date : 8/8/2010